Skip to main content

Fastenal VHUB Facility

Kitchener, Ontario

New Canadian Distribution Facility

Melloul-Blamey assisted in the site selection, planning and pre-development process of this project. Responsibilities included full consultant tendering and retention, design development and value engineering.
Construction of the first phased consisted of a new 2 storey 1,243 m² office space, 9,329 m² warehouse and load dock space and an automated 2,601 m² Automatic Storage and Retrieval System. The site has been planned for future phases and a maximum build out to suit the 25 year plan of Fastenal. The phase two warehouse expansion was completed in 2020.


Consultants

ABA Architects Inc., MTE Consultants, Collins Engineering, Rombald Inc.

Sector

Project Duration

Oct 2013-Nov 2014 / Sept 2019-Aug 2020

Size

140,000 & 100,000 sq ft

Value

$14,000,000 & $8,100,000

Project Type

Construction Management

Client

Fastenal Company